Project completed in April 2021, consisting of the interior adaptation of an area of 85 m2 for corporate offices.
• Function performed
General Contractor
• Intervened Elements
Power supply systems, construction of drywalls and ceilings, floors, lighting fixtures, doors, glass partitions, painting, HVAC, fire suppression system, access control, and finishes.
• Challenges and Achievements
Work on this project was to be carried out mostly at night and on weekends. Despite this, the project was delivered on time.