Project completed in March 2017, consisting of the adaptation of 140 m2 of the premises of a spa /
aesthetic.
• Function performed
Architectural design, General Contractor and interior design.
• Intervened elements
Electrical power systems, lighting, partitions, ceilings, air conditioners, plumbing, painting and general
joinery.
• Challenges and Achievements
For contractual reasons of the premises the work had to be completed in no more than 2 months and this
including the design process.
The work was completed on time and in perfect operating condition.